23 March 2020 Keywords: Open access regulation, Captive power plant, Cross-subsidy Surcharge, Transmission Charge, Wheeling charges, Third Party Sale, RE Forecasting


(Open Access and Captive  Generation) Summary: 

The APERC notified draft for 2nd amendment to its open access regulation 2005, which proposes to impose 100% transmission and wheeling charges, distribution losses, and cross-subsidy surcharge for captive use or third-party sale.

CER Opinion:

1. Concern regarding RE intermittency issues could be addressed by tightening forecasting regulations along with the application of deviation settlement mechanism (DSM) can help ameliorate this impact to some extent. 
2. Removing exemptions may only reduce benefits for captive and open access consumers, 
3. The small revenue generated by relaxing exemption may not have much effect on DISCOMs financial performance. 